Okay, so I had a few stressful days coordinating work on the exterior- the foundation guys needed water to mix the cement. No water! The plumber was called, the lockbox wouldn’t open and he couldn’t get in. Next up, newbie that I am, I had the roofer scheduled to be there at the same time men were under the house, not good. They were able to shift the work around to accommodate the roofer. Thanks guys!

Construction materials:

There were cracks in one outside wall that had to be repaired. Since the mortar needs time to “cure” or “set” I had to push back the exterior painter until the 14th.

^^The darker areas are the new mortar.

And now, I am the proud owner of a new roof!